Financial Interaction

Dealing With Quality Renovations

Financial Dealings Summary with Contractor 

Quality Renovation,(Mr. Ghandour)

 

Initial Agreement

  • Contract signed July 25, 2025 for $2,835 total ($2,700 + $135 GST).

  • $1,000 deposit paid July 25.

  • Remaining balance ($935) to be paid only upon full completion.

Payments Made

  • $1,900 total paid before meaningful completion:

    • $1,000 deposit.

    • Additional $900 post-demolition request.

  • Contractor acknowledged receiving these amounts but delayed issuing receipts, despite repeated promises. Eventually submitted an invoice for $1900.

Work Issues

  • Posts poured on Aug 6 were later found to be misaligned (confirmed with string line and photos).

  • Contractor removed materials (posts and chain link) from property without consent, later denying it, then admitting it, then denying again.

  • Work repeatedly delayed despite at least 10 promised start/completion dates.

  • Contractor failed to carry out Call Before You Dig obligations, pushing responsibility onto the homeowner.

Negotiations Over Refund

  • Aug 21: After Shawn’s formal letter, contractor said he would agree to Option 1 (partial refund) but rejected the $1,400 refund request, claiming he had done “more than $500 worth of work.”

  • Aug 22: Contractor floated a figure of $1,200 refund.

  • Aug 22 (later): Shawn countered with $1,400 refund and then a $1300 midpoint compromise.

  • Contractor agreed in principle to a refund but attached conditions, such as Shawn agreeing not to post reviews.

  • Shawn followed with conditions that payment was dependent on future contractor validating or denying the “work” that “Quality Reno” did . Quality Reno would be responsible for a greater amount if posts were not suitable.

Payment Promises and Delays

  • Shawn outlined numerous safe and reliable payment methods. Contractor promised to send a cheque and resisted Interac transfer or other secure options (even though Shawn originally paid through Interac Bank payment meeting all time frames.)

  • Contractor surprisingly claimed he was out of the country until Sept 17, so cheque would have to be mailed by his “accounting firm.”

  • Shawn asked for registered mail with tracking, which the contractor agreed to but never provided proof for.

  • Contractor was offered a 24 hour period to offer proof of registered mail. Failed to produce it.

  • By Aug 30, the cheque still had not arrived despite repeated promises (“Hi it’s a long weekend I promise you will get payed”).

  • Throughout, contractor shifted stories (sometimes saying the cheque was sent, sometimes blaming delays, sometimes refusing further communication).

Key Misrepresentations / Reneging

  • Refund Amount: Mischaracterized his stance by implying “at least $500 worth of work” justified reducing refund.

  • Payment Method: Refused reimbursement method that would have been consistent of what he requested from Shawn, then reneged and insisted on cheque only.

  • Delivery of Funds: Promised multiple times to send or have mailed by accountant, but never provided verification or completed payment.

  • Materials: Gave conflicting statements about taking chain link and posts — denied, admitted, denied again.

  • Timelines: Consistently promised specific dates for completion or refund, then failed to follow through.

  • No refund as of September 1 2025.